The single biggest mistake people make when moving is underestimating how long utility connections take. This guide gives you realistic timeframes so you can plan with confidence.
Electricity connection timeline
Electricity is typically the easiest and fastest utility to connect:
- Account transfer (warm): 1–2 business days. The previous occupant had power and you're registering as the new account holder. Often done remotely with no technician required.
- New connection after disconnection (cold): 3–5 business days. A technician must physically reconnect the supply at the meter. Some properties may require an electrical inspection certificate first.
- New build: 2–6 weeks. Requires a meter to be installed, a licensed electrician's certificate, and network connection. Coordinate with your builder.
Action required 5 days before moving: Call your electricity retailer to arrange account transfer to your new address. Simultaneously, arrange disconnection of your old address for your move-out date.
Gas connection timeline
- Account transfer: 2–5 business days
- Gas reconnection (after disconnection): 5–7 business days. A licensed gasfitter must reconnect and test the supply for safety.
- New gas meter installation: 2–4 weeks. Required for new builds or properties that have never had gas.
Note: Natural gas is not available in all areas. Western Australia, the ACT and some regional areas have limited or no gas networks. Check whether gas is connected at your new property before arranging anything.
Internet (nbn) connection timeline
This is where people most frequently encounter delays. nbn connections require more steps than electricity or gas:
| Connection type | Typical lead time | Technician needed? |
|---|---|---|
| Existing connected address (warm) | 3–10 business days | Usually no |
| Never-connected address | 2–4 weeks | Yes |
| FTTP upgrade | 4–8 weeks | Yes |
| Fixed wireless (rural) | 2–4 weeks | Yes (antenna install) |
| 5G home wireless | Same day to 3 days | No (self-install kit) |
The highest-risk scenario is a property that has never had nbn connected. If your new home is a newly built house or a property in an area that recently joined the nbn footprint, allow 4–6 weeks minimum and book immediately after your address is confirmed.
Water connection timeline
Water is generally the simplest utility to manage when moving. In most Australian states, you notify the water authority that you've moved in and billing transfers to you automatically. There's no physical connection process for existing properties. For new builds, a licensed plumber must connect the property to the water main — allow 2–4 weeks.
Connection timeline summary
| Utility | Existing property | Never connected | New build |
|---|---|---|---|
| Electricity | 1–2 days | 3–5 days | 2–6 weeks |
| Gas | 2–5 days | 5–7 days | 2–4 weeks |
| nbn Internet | 3–10 days | 2–4 weeks | 4–8 weeks |
| Water | Same day (notify only) | Same day | 2–4 weeks (plumber) |
Our recommendation: Book electricity and gas 5–7 business days before moving. Book internet (nbn) 3–4 weeks before moving. Notify your water authority in the week of your move. This timeline eliminates the risk of being without any essential service on day one.
Frequently asked questions
What is the fastest utility to connect when moving?
Can I get same-day electricity connection?
What is a 'cold' connection vs a 'warm transfer'?
Who pays for utilities during a settlement period?
Can I have internet on day one of moving in?
Keep reading
Let Pick A Deal coordinate all your connections
We compare plans from our provider panel and help coordinate your connection — completely free.